Delhi Metro adopts unique construction method to complete work on Trilokpuri stretch
Jun 25, 2021
New Delhi [India], June 25 : To expedite work on the Trilokpuri section of Pink Line, the Delhi Metro adopted a unique construction method by using steel girders instead of the conventional concrete ones.
As per a statement issued by Delhi Metro Rail Corporation, the construction of concrete girders would have required the establishment of a casting yard and it would not have been feasible to set up a casting yard for such a small stretch within a short duration of time.
"Therefore, steel girders were installed on this stretch. A total of 40 steel girders have been placed on 10 spans for the 290 meter-long section. These steel girders have been fabricated and brought from a workshop at Ambala in Haryana. This has not only saved time but also there was no need to create a separate casting yard for the concrete casting of the girders," the statement said.
Delhi metro informed that the length of these girders varies from 16 to 38 meters, and the height of the viaduct stands at about 8 to 9.5 meters. A curved span of radius 200 meters is also a part of this stretch.
Earlier, for the construction of the Chhattarpur Metro station also, DMRC had adopted a similar method of using steel structures because construction of that station was also delayed due to land acquisition issues.
"The work on installing these steel girders and casting of deck slab was completed in April just before the second surge of the Covid-19 pandemic. This was a significant achievement because the civil construction on this stretch was started in early 2020 and was repeatedly hampered by the pandemic-induced lockdowns and issues such as the non-availability of workforce. Now, track laying and other ancillary works have commenced on this stretch between Mayur Vihar Pocket - 1 and Trilokpuri Sanjay Lake following the completion of civil work. In addition, Overhead Electrification work is also under progress," Delhi Metro said.
It further informed that the track laying work of Metro is expected to be completed by the end of June, and preliminary trials are expected to start thereafter.
"All efforts are being made to further expedite the progress of work on this particular stretch. The section shall be operational immediately after receiving the mandatory clearances from all concerned authorities," it added.
Once completed, this section will connect the two ends of Pink Line and will provide seamless connectivity to a long range of localities in the National Capital Region.
Important transport hubs such as Nizamuddin Railway Station, Sarai Kale Khan ISBT, Anand Vihar Railway Station, Anand Vihar ISBT, Delhi Cantt. Railway Station, and prominent markets like Dilli Haat - INA, Sarojini Nagar and Lajpat Nagar will get direct connectivity through this corridor.
This corridor will further be extended from Majlis Park to Maujpur in Phase - IV, making it the longest single Metro corridor in India at approximately 70 kilometers.
After completion of the Phase - IV, the Pink Line will also become the only Ring Corridor of Metro in the country.
DMRC is also developing an internal road below the viaduct at Trilokpuri which will connect the Vasundhara Road and Trilokpuri Road. The road will be 140 metres in length, and is expected to help in decongesting the area and easing the traffic scenario.
While the presently operational sections of the Pink Line were made functional in 2019, this small stretch got delayed due to the unavailability of encumbrance-free land.
"After following the due process of law, the land was acquired and R and R (Rehabilitation and Resettlement) of Project Affected Persons was done for commencement and completion of construction work," Delhi Metro added further.